The wastewater plant has a design capacity of 5.9 mg/d and is
currently operating at 3.6 mg/d average daily flow.
Lee & Ro is the design
engineer to assist in the construction management services for a $20
million plant renovation and improvements project at the 5.9 mg/d
wastewater treatment plant.
The proposed improvements will consist of the construction of three
(3) 80-foot diameter secondary clarifiers, three (3) Biolac lagoons,
a blower/MCC building and several smaller structures, such as
distribution boxes, flowmeters, etc.
LandMark Consultants, Inc. is the geotechnical engineer of the record for this
project. We provided geotechnical investigation in
2008 for Lee & Ro.